It has been more than five years since we started our prestigious Bridge County Project (in the year 2011) and the seeds sown have borne fruit! We are proud to inform you that out of the 557 units that we are coming out with, 320 units have already been sold and occupied and we have an ever increasing & thriving Community enjoying the wonderful spaces at Bridge County. Another important update would be that more than 10 villas are already occupied and 30 villas are up for sale, out the projected 50 villas that we are constructing. Apart from this we would like present an update on what’s happening at Bridge County – A.P.’s largest Integrated Township in Rajahmundry-

  1. First Tower in Phase-2, Block A54 has been handed-over.
  2. Finished works @ 20 villas and handed over.
  3. Transformer yard has been established and provided independent EB Meters for all houses in phase-1.
  4. STP Civil works and equipment installation are completed.
  5. Approvals work for other blocks in phase-2 is in progress.
  6. Construction work for new Blocks in phase-2 on brisk pace.
  7. Kerbs have been installed along the township roads.
  8. Road works in Phase-2 are nearing completion.

It is our endeavour to keep you updated with the progress and if you have any sales related queries about  Bridge County please call us at 7680002288